Here is the first update on the new wagon.  We will post further updates as the progress moves forward.

This week the cab completed fabrication and is off-site for protective coating application. The pump house is in fabrication and the body panels have completed the weld process. 

 

On the next report, the cab should complete the paint process. The pump house should complete fabrication and begin the paint process and the body should near completion in fabrication.

Due to the Pierce Mfg. 4th of July production shut down, our next report will be on July 17, 2009